Designed specifically for demilitarization project of 1 million rounds of cal. 100MM tank ammo
- Operated in field conditions
- Nominal capacity: 60 – 72 rounds per hour
- Operated for 2 shifts a day
Currently installed technologies
- 14 containers as processing buildings
- Defuzing/depriming machine in an explosion-resistant bunker
- Pull-away machine
- Gun propellant recovery
- TNT melt-out station
- Others to be installed
![]() |
![]() |
![]() |
|
![]() ![]() |
|
![]() |
|
Disassembly unit A - D
- A2/A3: ammo degreasing and putting on conveyor
- A4: machinery room
- B1: preparation room for defuzing/depriming
- B2: bunker for defuzing/depriming operation
- C1: conveyor with integrated pull-away machine
- D1: shipping projectile and cartridge case
Processing units (separate)
- E1/E2: gun propellant recovery from cartridge cases
- T1-T4: TNT melt-out station (control room, steam generator, melt-out units)
Storage magazines (separate)